Sunderland Royal Hospital Endoscopy unit

A £6m facility, purpose-designed by Dunwoodie Architects and Desco, was created at Sunderland Royal Hospital to rationalise and improve endoscopy services in the area. The new unit has increased capacity and the environment meets best practice standards for patient flow, quality, experience and safety, as well as providing the latest technologically advanced equipment.

The pathology department, which was situated within the existing footprint, was to be reduced in size to accommodate an improved endoscopy department. All non-urgent pathology tests would be relocated from Sunderland to a new centralised pathology unit at Gateshead Queen Elizabeth Hospital, serving the wider area.

Keeping essential pathology services running

The Sunderland pathology department would continue to include a ‘hot laboratory’, which carries out urgent clinical tests, while non-urgent ‘cold’ tests would be provided at Gateshead. Phased working was employed to allow this hot lab to stay operational throughout the project.

The hot lab operates the only blood analysis machine in the North East of England, which had to be available 24 hours a day, 7 days a week. 

Endoscopy services

Putting user needs first

NHS services remained in use around the endoscopy area, including the pathology lab as well as operating theatres.

Careful planning and collaboration ensured that we avoided disruption to theatre staff and patients. Noisy activities, such as drilling and bracketing, had to be carried out early in the morning before any medical operations started.

Pathology services installed

The works to the pathology department were phased into three stages to enable the client to continue working, with our operations planned on a weekly basis.

Endoscopy services installed

The works for the new endoscopy department, the larger of the two projects, involved a full stripping out of the ward and re-installation of services for four endoscopy rooms, with the potential for two more in the future.  Daily work was meticulously planned to ensure the programme continued on track and the handover was not delayed.

 

Related news

  • Planning submitted for another 315 homes...

    Planning submitted for another 315 homes...

    Urban Union and Barton Willmore have submitted plans for the next phase of regeneration at the Pennywell Living development.
  • Building begins on new council homes in ...

    Building begins on new council homes in ...

    North Lanarkshire Council’s latest sod cutting event marked a new housing development at the former Old School Court in Coatbridge.
  • Plans submitted for new neighbourhood in...

    Plans submitted for new neighbourhood in...

    Robertson Partnership Homes, Redco Slackbuie Ltd and Caledonia Housing Association have submitted plans for 67 new homes.

Related blog posts

  • Offsite manufacturing: installing windows in closed timber panels

    Offsite manufacturing: installing windows in closed timber panels

    How offsite manufacturing techniques, in particular installing windows in closed timber panels, benefits construction.
  • Back to the floor: engineering apprenticeships

    Back to the floor: engineering apprenticeships

    Robertson Engineering Services Managing Director, Darren Clarke, meets with mechanical and electrical engineering apprentices.
  • A route in to modern apprenticeships

    A route in to modern apprenticeships

    Robertson’s Dundee office has seen various young people start apprenticeships and progress in their careers in the past few years.